John Cochran Building 29 Demo
Scope & Delivery
The John Cochran VAMC Building 29 Demolition project involved the complete removal of a 19,150‑square‑foot facility identified as containing 100% contaminated materials. Awarded as a sole‑source contract by the Department of Veterans Affairs due to RKE’s previous exceptional performance, the project required comprehensive demolition, hazardous waste abatement, and site restoration within an active medical campus.
Work included full building demolition, hazardous materials removal and disposal, structural concrete demolition, earthwork and grading, and installation of new concrete flatwork, sidewalks, stormwater features, and erosion control systems. Additional improvements included granite curbing and permanent vegetation establishment to return the site to a safe, stabilized condition. RKE self-performed approximately $776,793.44 of the overall scope.
RKE also provided complete project leadership, including project management, quality control, on‑site safety oversight, and daily coordination with VAMC stakeholders to ensure all operations complied with federal, environmental, and medical‑facility safety requirements.
Safety Record: The project was completed with zero recordable incidents, reflecting RKE’s commitment to safe, compliant, and efficient demolition operations on sensitive federal sites.